Building Over or Near a Public Sewer in Yorkshire

By the Resolve Structural team · Updated 16 November 2026

The drain a rear extension lands on is very often not yours alone. If it is a public sewer, the sewerage company has a say in what is built over or beside it, and the foundations have to be designed around it. Yorkshire Water says you need its consent before you start any building works over or within 3 metres of a public sewer.

One check first: your sewerage company may not be Yorkshire Water. Yorkshire Water's own advice is to check which company bills you for sewerage services, because that is the company to contact.

How to tell if a sewer runs under the extension

Yorkshire Water's definitions are the place to start. A drain serves just your property. A lateral drain is the length of that drain outside your boundary. A sewer collects from the drains of more than one property. A pipe in your garden that also takes your neighbour's waste is therefore a sewer, however small it is.

Most such pipes are now public. Regulations made in 2011 required schemes for the adoption of private sewers and lateral drains that connected to the public sewer immediately before 1 July 2011, with 1 October 2011 as the date they passed to the sewerage company. Yorkshire Water adds two cautions: on a property built after 2011 the developer may not have asked for the pipework to be adopted, and its sewer records are not complete, because not all underground pipes are recorded.

Yorkshire Water's suggested checks are:

  • Your property's deeds
  • Any drainage plans your local council holds for the property
  • Your builder, architect, estate agent or the previous owner
  • Signs on the ground - a manhole cover, an access point or a shared gully inside your boundary
  • Your neighbours, who may know whether their drainage runs through your land
  • Yorkshire Water's public sewer records, bearing in mind they are unlikely to show drains inside your boundary
  • A CCTV drainage survey or tracing by a competent drainage contractor

Of these, the survey is the one that gives a designer a line and a depth to work from.

When consent is needed

The Building Regulations come at the same 3 metres from the other side. Requirement H4 requires an extension, or underpinning, to be carried out in a way that is not detrimental to the building or to the continued maintenance of the sewer, and the guidance in Approved Document H applies to building over or within 3m of the centreline of a drain or sewer shown on the sewer records.

There are limits on what will be accepted at all. Yorkshire Water says you will not be permitted to build over access points - manholes, gullies or inspection chambers - or near pipes larger than 225mm in diameter or deeper than 3m. Approved Document H gives the same figures, and adds that no more than 6m of drain or sewer should run under a building without the owner's permission.

How consent is obtained depends on the route. If you have applied for Building Regulations approval, Yorkshire Water says your local authority building control will consult it on your behalf - ask for a copy of the response. If you have not, you can send Yorkshire Water a build-over enquiry directly. There is an application fee, which Yorkshire Water publishes on its building over a public sewer page; we link to it rather than repeat a figure that changes.

What the application needs

For a direct build-over enquiry Yorkshire Water asks for:

  • Existing site information, including the type of development proposed
  • An existing layout drawing of the property, showing any sewers, lateral drains, manholes and gullies you know of
  • A proposed layout drawing showing where the work will be, with the same drainage marked on it

Where the work is affected by existing drainage, the drawings need to show both the existing and the proposed drainage system. The answer is either an acceptance letter or a letter setting out objections and the alternatives, which might be changing the design to avoid the sewer or a minor alteration to the sewer itself. Yorkshire Water advises keeping the acceptance letter, because you may need it for Building Regulations approval or when you sell.

Foundation and drainage design near sewers

This is the engineering part. Approved Document H section H4 says the building must not overload or damage the pipe during or after construction. Its guidance includes:

  • Where the drain or sewer under the building is less than 2m deep, the foundation is extended locally so that the pipe passes through the wall, with measures to prevent damage where it does
  • Where it is more than 2m deep to invert and passes beneath the foundations, the foundations are designed as a lintel spanning over the line of the pipe, extending at least 1.5m either side of it, so that no load is transmitted onto the drain or sewer
  • At least 100mm of granular or other flexible filling round a pipe that runs under a building
  • A drain trench should not be excavated lower than the foundations of any building nearby

In practice the foundation drawings show the surveyed line and depth of the sewer, the foundation levels either side of it, and how the wall bridges it. We design those details as part of foundation design and drainage design, together with the new drainage for the extension - see drainage falls explained for the gradients - and they go into the Building Control package.

Diverting a sewer

Where building over is not acceptable, the pipe can sometimes be moved. For small domestic cases Yorkshire Water has a minor alteration route - moving or removing a manhole, gully or inspection chamber, or renewing pipework - limited to pipes inside your boundary that are up to 225mm in diameter, less than 3m deep and no more than 20m long. It needs Yorkshire Water's agreement first and a competent drainage contractor to carry it out.

Anything larger is a diversion under section 185 of the Water Industry Act 1991. The section lets a person with an interest in land require the undertaker to alter or remove a pipe where that is necessary for a proposed improvement of the land. The undertaker must comply unless the requirement is unreasonable, the duty does not cover apparatus in a street, and the person who serves the notice pays the undertaker's charges. Yorkshire Water's diversions page says no diversion may start until the section 185 agreement is in place and warns that diversion "can be a lengthy process". The submission includes layout plans, longitudinal sections, manhole schedules, construction details, a camera survey and hydraulic calculations.

If you find a sewer after work has started

Stop and tell Yorkshire Water. Its guidance is to get in touch at the earliest opportunity if the drainage on site turns out to be different from what was expected, even where an acceptance letter has already been issued.

Sources

Frequently asked questions

Do I need Yorkshire Water's consent to build near a public sewer?

Yes, if the work is over or within 3 metres of a public sewer - that is Yorkshire Water's rule. If you have applied for Building Regulations approval, building control consults Yorkshire Water on your behalf; ask for a copy of the response.

How much does a build-over application cost?

Yorkshire Water charges an application fee for a direct build-over enquiry and publishes the current figure on its building over a public sewer page. We do not repeat it here because it changes.

Can I build over a manhole?

No. Yorkshire Water says you will not be permitted to build over access points such as manholes, gullies and inspection chambers, and Approved Document H says the same of manholes and inspection chambers on a sewer. Moving one is a minor alteration to the sewer, which needs Yorkshire Water's agreement first.

Is the drain I share with my neighbour a public sewer?

Usually. A pipe that collects from more than one property is a sewer, and private sewers connected to the public network were transferred to the sewerage companies in 2011. The exception Yorkshire Water points out is newer property, where the developer may not have had the pipework adopted - check the deeds.

What if the sewer is too big or too deep to build over?

Pipes larger than 225mm in diameter or deeper than 3m are outside what Yorkshire Water will normally allow building near. The options are to change the design so the building stays clear of the pipe, or to apply for a diversion under section 185 of the Water Industry Act 1991, which Yorkshire Water describes as a potentially lengthy process.

Can you deal with the application for us?

Yes. We produce the build-over details - the foundation design over or beside the sewer and the drainage drawings - and can handle the application with the water company alongside the Building Control package.

Let’s discuss
your project.

Get practical advice and a clear quote from our experienced engineering team.

  • Experienced Engineers

    Decades of combined expertise across residential, commercial and civil engineering.

  • Clear Communication

    We keep you informed at every stage of your project.

  • Practical Solutions

    Engineering that is buildable, compliant and cost-effective.